{"postcode":null,"status":"Approved","decision_agency":"Borough","subdivision_of_building":"The proposal includes the upward extension of 147-161 Hounslow High Street to provide six additional units. These units are comprised of two on the proposed second floor and four on the proposed third floor","appeal_start_date":null,"cil_liability":true,"decision_conditions":["Condition : 1 - The development hereby permitted shall begin not later than three years from the date of this decision.\r\nReason: In order to comply with Section 91 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.","Condition : 2 - The development hereby permitted shall be carried out in accordance with the following approved plans and specifications: 2411-P-01-0200-ZXX Rev 01, 2411-P-01-0010-Z00 Rev 02, 2411-P-01-0011-Z01 Rev 02, 2411-P-01-0012-Z02 Rev 02, 2411-P-01-0022-ZEA Rev 01, 2411-P-01-0023-ZWE Rev 01, 2411-P-01-0030-ZAA Rev 01, 2411-P-01-0031-ZBB Rev 01, 2411-P-01-0210-Z01 Rev 01, 2411-P-01-0211-Z01 Rev 01, 2411-P-01-0221-ZSO Rev 01, 2411-P-01-0230-ZSO Rev 01, Daylight Sunlight Report November 2025, Flood Risk Assessment & SUDS Strategy for Planning dated October 2025, Noise Impact Assessment October 2025, Transport Statement Received 10 December 2025\r\n2411-P-01-0212-Z02 Rev 02, 2411-P-01-0215-ZXX Rev 02, 2411-P-01-0223-ZWE Rev 02, 2411-P-01-0330-ZAA Rev 02, 2411-P-01-0331-ZBB Rev 02, 2411-P-01-0340-ZAA Rev 02 Received 17 February 2026\r\n2411-P-01-0213-ZXX Rev 03, 2411-P-01-0220-ZNO Rev 03, 2411-P-01-0222-ZWE Rev 03 Received 02 March 2026\r\n2411-P-01-0213-Z03 Rev 04 Received 13 March 2026\r\nSustainability and Energy Statement Received 19 March 2026 \r\n\r\nReason: In order to ensure the development is carried out in accordance with the planning permission.","Condition : 3 - The development hereby permitted shall be implemented in accordance with the recommendations of the approved Noise Impact Assessment dated October 2025. The sound insulation works shall be completed before the building is first occupied or brought into use and retained as such thereafter.\r\nReason: In order to protect future occupiers from unacceptable noise levels.\r\n","Condition : 4 - No development shall take place until full details and samples of all materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the local planning authority. Details must include a detailed schedule of materials, a photographic sample board and rendered drawings, elevations and sections at a sufficient scale (1:20 or 1:50) to illustrate how all external materials will appear together.\r\nThe details shall include: \r\n(a) Cladding materials (including specifications where relevant);\r\n(b) Roof covering; including parapet coping / capping materials, dormers and canopies;\r\n(c) Window types; and sectional drawings of reveals / sills / head details \r\n(d) Balcony details (including soffits, panels and frame);\r\n(e) All privacy measures (including obscure glazing details, privacy screens etc.);\r\n(f) Balustrading treatment to balconies and roof areas (including details / sections / materials); and handrails\r\n(g) Any other materials/details / fittings to be used (including solar panels, extract vents, rainwater goods, boiler flues etc.), with sections and on-site samples where appropriate.\r\nThe development shall then be carried out in accordance with the approved details and maintained as such thereafter\r\nReason: In order to protect the appearance of the area\r\n","Condition : 5 - Prior to occupation, details of both hard and soft landscape works have been submitted to and approved in writing by the local planning authority. These details shall include:\r\n(a) a statement setting out the design objectives and how these will be delivered; \r\n(b) existing and proposed finished levels or contours; \r\n(c) means of enclosure/boundary treatment(s) and retaining structures;\r\n(d) hard surfacing materials; \r\n(e) minor artefacts and structures (e.g. furniture, play equipment, refuse or other storage units, signs, lighting, CCTV etc.); \r\n(f) proposed and existing functional services (e.g. drainage, power, communications cables, pipelines etc. indicating alignments, levels, access points, supports as relevant);  \r\n(g) renewable energy installations (where relevant);\r\n(h) planting plans, written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants, noting species, plant sizes and proposed numbers and densities where appropriate; and\r\n(i) an implementation programme (including phasing of work where relevant).\r\nThe landscaping works shall comply with the requirements specified in BS 3936 (1992) 'Specification of Nursery Stock Part 1 Trees and Shrubs', and in BS 4428 (1989) 'Recommendations for General Landscape Operations', and shall be carried out in accordance with the approved details before the development hereby permitted is first occupied or brought into use, or such other date(s) as may be specified in the agreed implementation programme.\r\nReason: In order to ensure a satisfactory appearance of the site and the area and to promote biodiversity.\r\n","Condition : 6 - No development shall take place until a Construction Logistics Plan (CLP), written in accordance with current TfL guidance, has been submitted to and approved in writing by the Local Planning Authority. The CLP shall include: [delete or add items as necessary]\r\n(a)\ta site plan (showing the elements set out below);\r\n(b)\tconfirmation that a pre-start record of site conditions on the adjoining public highway will be undertaken with Hounslow Highways and a commitment to repair any damage caused;\r\n(c)\tprovision for the parking of vehicles of site operatives and visitors;\r\n(d)\tprovisions for loading, unloading and storage of plant and materials within the site;\r\n(e)\tdetails of access to the site, including means to control and manage access and egress of vehicles to and from the site for the duration of construction including phasing arrangements;\r\n(f)\tdetails of vehicle routeing from the site to the wider strategic road network;\r\n(g)\tthe erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate;\r\n(h)\tprovision of wheel washing facilities at the site exit and a commitment to sweep adjacent roads when required and at the request of the Council;\r\n(i)\ta scheme for recycling/disposing of waste resulting from demolition and construction works; \r\n(j)\tmeasures to ensure the safety of all users of the public highway especially cyclists and pedestrians in the vicinity of the site and especially at the access;\r\n(k)\tcommitment to liaise with other contractors in the vicinity of the site to maximise the potential for consolidation and to minimise traffic impacts;\r\n(l)\tno deliveries before 9.30am and after 3pm to avoid school opening and closing times and peak hours, unless otherwise agreed in advance with the council and details of a booking system to avoid vehicles waiting on the public highway;\r\n(m)\tall necessary traffic orders and other permissions required to allow safe access to the site to be secured and imp","Condition : 7 - No development shall take place until the applicant has entered into a binding arrangement with the Council to make an agreed contribution to the Council's Carbon Offset Fund, in accordance with the zero carbon strategy set out in the Energy Statement hereby approved to an amount that equates to the shortfall in required energy savings to meet the 'zero carbon' target.\r\nReason: In order to ensure the development meets sustainability standards. ","Condition : 8 - a) The development hereby permitted shall be implemented in accordance with the approved Energy Strategy.\r\n(b) Prior to first occupation of any dwelling within the development hereby approved evidence (e.g. photographs, installation contracts and As-Built certificates under the Standard Assessment Procedure/National Calculation Method) shall be submitted to the local planning authority and approved in writing to show that the development has been constructed in accordance with the approved Energy Strategy, and any subsequent approved revisions, and achieved a 67% reduction in emissions.\r\n(c) Upon final commencement of operation of any low and zero carbon technologies, suitable devices for the monitoring of the low and zero carbon technologies shall have been installed, and the monitored data shall be submitted automatically to a monitoring web-platform at daily intervals for a period of three years from the point of full operation. The data shall be made available to the local planning authority on request for a period of five years.\r\nReason: In order to ensure that the development makes the fullest contribution to minimising carbon dioxide emissions.","Condition : 9 - Prior to first occupation of the building(s) hereby approved, the development shall have been constructed to achieve an internal water use of 105 litres/person/day or less.\r\nReason: In order to protect and conserve water supplies and resources.","Condition : 10 - Before the development hereby permitted is first occupied or brought into use, the Local Planning Authority shall be informed of the agreed naming and numbering of the proposed dwellings so that arrangements can be put in place to ensure that, with the exception of a person eligible for a disabled person's badge issued pursuant to section 21 of the Chronically Sick and Disabled Persons Act 1970 (or similar legislation), no resident of the development shall obtain a resident's parking permit. Any occupiers of the approved development shall surrender any such permit wrongly issued or held.\r\nReason: In order to protect the free flow and safety of traffic on nearby highways and to support sustainable transport objectives.","Condition : 11 - Prior to the first use or occupation of the development full details (including manufacturers' specifications) of secure covered cycle parking facilities that accord with the West London Cycle Parking Guidance (for not less than 16 bicycles) for the occupants of, and visitors to, the development shall be submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be fully implemented and made available for use before the development is first occupied or brought into use, The approved facilities shall be thereafter retained for use at all times without obstruction. \r\nReason: In order to support sustainable transport objectives."],"actual_commencement_date":null,"pp_id":"14504070","decision_target_date":"09/04/2026","valid_date":"10/12/2025","lpa_app_no":"P/2025/3543","locality":null,"appeal_decision_date":null,"parking_details":{"no_existing_cycle":28,"no_proposed_cycle":44,"net_cycle":16},"decision_process":null,"street_name":null,"last_synced":"2026-04-14T02:11:51.364Z","site_number":null,"centroid_easting":0.0,"polygon":{"geometries":[{"coordinates":[[[514019.5495664859,175699.52683626424],[514000.7789988852,175749.71604726498],[514000.40914654464,175750.71688582734],[514024.26889540895,175759.7159468637],[514024.5092883882,175759.06601448313],[514039.14904655877,175764.28607105982],[514046.9191601329,175741.4261353679],[514054.869072553,175721.27606668058],[514057.47169033345,175715.45334252267],[514053.9691535526,175712.77682384884],[514047.5689802399,175707.97609871754],[514043.27939512965,175704.686843395],[514039.2589019154,175701.57607281295],[514023.7489781228,175691.60689597283],[514022.53902900376,175693.81610462052],[514019.5495664859,175699.52683626424]]],"type":"Polygon"}],"type":"geometrycollection"},"ward":"Hounslow Central","centroid_northing":0.0,"application_type":"All Other","uprn":null,"lapsed_date":"06/04/2029","actual_completion_date":null,"decision":"Approved","site_name":null,"borough":"Hounslow","last_date_consultation_comments":"05/01/2026","application_type_full":"Full planning permission","url_planning_app":"https://planningandbuilding.hounslow.gov.uk/NECSWS/ES/Presentation/Planning/OnlinePlanning/OnlinePlanningOverview?applicationNumber=P/2025/3543","decision_date":"07/04/2026","bo_system":"Northgate M3","development_type":"Minor dwellings","appeal_status":null,"date_building_work_completed_under_previous_permission":null,"description":"Erection of a part third floor front extension to provide four additional flats and a part second floor rear extension to provide two additional flats, with associated landscaping, cycle parking and refuse storage","appeal_decision":null,"date_building_work_started_under_previous_permission":null,"epc_number":null,"last_updated":"2026-04-13T09:10:10.897Z","centroid":{"lon":-7.55716,"lat":49.766807},"lpa_name":"Hounslow","secondary_street_name":null,"application_details":{"affordable_housing_fast_track":false,"phasing_details":[{"phase_detail":"Entire development ","intended_completion_date":"09/2026","intended_commencement_date":"03/2026"}],"total_gia_gained":526,"site_area":0.217,"total_gia_existing":4587,"total_gia_lost":0,"existing_proposed_floorspace_details":[{"gia_existing":2657,"use_class":"C3","gia_gained":526,"gia_lost":0},{"gia_existing":1930,"use_class":"EA","gia_gained":0,"gia_lost":0}],"projected_cost_of_works":"Up to £2m","scheme_phasing":true,"rain_water_harvesting":false,"grey_water_reuse":false,"building_details":[{"no_storeys":4,"max_height":14.5,"building_ref":"147-161 Hounslow High Street"}],"green_suds":false,"surface_water_discharge_percentage_reduction":0,"non_residential_details":{"total_non_resi_gross_internal_floor_area_to_be_gained":0,"total_non_resi_gross_internal_floor_area_to_be_lost":0,"total_gia_gained":526,"total_gia_existing":4587,"total_gia_lost":0},"garden_land_lost":false,"residential_details":{"total_no_proposed_residential_units_shared_equity":0,"total_no_proposed_bedrooms":10,"total_no_proposed_residential_units":7,"total_no_proposed_residential_units_london_living_rent":0,"total_no_proposed_residential_affordable_units":0,"total_no_proposed_residential_units_affordable_rent":0,"total_no_existing_residential_units":0,"total_no_proposed_residential_units_discount_market_sale":0,"total_no_proposed_residential_units_discount_market_rent_charged_at_london_rents":0,"total_no_existing_residential_units_london_living_rent":0,"total_no_existing_residential_units_shared_equity":0,"total_no_existing_residential_units_market_for_sale":0,"total_no_existing_residential_units_intermediate":0,"total_no_proposed_residential_units_market_for_rent":6,"total_no_existing_residential_units_social_rent":0,"total_no_proposed_residential_units_self_build_and_custom_build":0,"total_no_existing_residential_units_discount_market_rent":0,"total_no_proposed_residential_units_market_for_sale":0,"total_no_existing_residential_affordable_units":0,"total_no_existing_residential_units_affordable_rent":0,"habitable_rooms_density":null,"total_no_existing_residential_units_london_shared_ownership":0,"total_gia_gained":526,"total_no_proposed_residential_units_social_rent":0,"total_no_existing_residential_units_london_affordable_rent":0,"dwelling_density":0,"total_no_existing_residential_units_discount_market_sale":0,"total_no_proposed_residential_units_starter_homes":0,"total_no_proposed_residential_units_london_affordable_rent":0,"total_gia_lost":0,"total_no_existing_residential_units_discount_market_rent_charged_at_london_rents":0,"total_no_existing_residential_units_starter_homes":0,"total_no_proposed_residential_units_discount_market_rent":0,"total_no_proposed_residential_units_intermediate":0,"affordable_percentage":0.0,"total_no_proposed_residential_units_london_shared_ownership":0,"residential_units":[{"change_type":"Gain","unit_type":"Communal Space","gia":157},{"provider":"Private","no_habitable_rooms":3,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":2,"tenure":"Market for rent","gia":62},{"provider":"Private","no_habitable_rooms":2,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":1,"tenure":"Market for rent","gia":55},{"provider":"Private","no_habitable_rooms":4,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":3,"tenure":"Market for rent","gia":91},{"provider":"Private","no_habitable_rooms":2,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":1,"tenure":"Market for rent","gia":50},{"provider":"Private","no_habitable_rooms":3,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":2,"tenure":"Market for rent","gia":61},{"provider":"Private","no_habitable_rooms":2,"change_type":"Gain","unit_type":"Flat Apartment Maisonette","no_bedrooms":1,"tenure":"Market for rent","gia":50}],"total_no_existing_residential_units_market_for_rent":0,"total_no_existing_residential_units_self_build_and_custom_build":0},"internal_resi_water_usage":110,"infrastructure_details":{"total_annual_pm_emissions":0,"green_roof_area":0,"no_resi_units_to_have_full_fibre":0,"no_new_water_connections_required":0,"no_homes_passive_cooling":0,"no_non_resi_units_to_have_full_fibre":0,"total_annual_nox_emissions":0,"waste_provision":true,"percentage_demolition_construction_material_recycling":0,"no_homes_to_have_electrical_heating":0,"mobile_network_operators_consultation":false,"fire_suppression_system_proposed":false,"no_new_gas_connections_required":0,"ghg_reduction_over_building_regulations":true},"ownership_status":"Private"},"wgs84_polygon":{"coordinates":[[[-0.359879,51.468786],[-0.360133,51.469241],[-0.360138,51.46925],[-0.359791,51.469326],[-0.359788,51.46932],[-0.359576,51.469364],[-0.359471,51.469157],[-0.359364,51.468974],[-0.359328,51.468921],[-0.359379,51.468898],[-0.359473,51.468856],[-0.359536,51.468827],[-0.359595,51.4688],[-0.359821,51.468714],[-0.359838,51.468734],[-0.359879,51.468786]]],"type":"Polygon"},"id":"Hounslow-P_2025_3543","reference_no_of_permission_being_relied_on":null,"title_number":null,"last_updated_by":"Northgate M3"}